Thursday, April 9, 2009

The first round the clock night bazaar in Vientiane to serve SEA GAMES 2009

(KPL) The Hong Thong Development Project (or Night Bazaar)would be operational on a round the clock basis to serve the tourists, commencing from the later part of the year and the purpose of this kind of operational hours is to attract more tourists to Vientiane capital.

This project, presently under construction, is located in Chanthaboury district, in front of Lao National Stadium.

President of Hong Thong Development Project, Mr Khamphay Somsana said that when the project was first proposed it was meant to serve the tourists and to offer them round the clock service.

Construction started in May 2008 and now 30 per cent of the building had been completed., the president of the project said.

“The project is part of Vientiane’s plan to generate more income to the city, especially to the business operators,” he said.

He added that the project would be opened as early as the opening day of the 25th Sea Games.

Funding for this project was made by four local investors, whose combined total investment was 25 billion kip and the authorities granted them a lease of 40 years, Mr Khamphay commented.

“We decided to construct the Night Bazaar because we found that the majority of tourists who visited Vientiane would not spend much time in it and as a result some of the Lao money goes to foreign countries,” said the president of Hong Thong Development Project.

The Night Bazaar would have 10,700 square metres of land, seven two-storey buildings, one restaurant, a public park and parking lot area, he
said.

The restaurant would offer a whole range of Lao food and the prices would be affordable, he added.

The handicraft products, he said would be on sale in the Night Bazaar in order to introduce to the foreign tourists the traditional culture of Laos and the products can be gifts to them, he said.

Tuesday, March 24, 2009

New sports stadium for the 25th SEA Games is now 90% completed



(KPL) Ninety per cent of the construction work of the new sports stadium for the 25th SEA Games has been completed.

The next stage is to carry out the decoration work for this infrastructure.
This was reported during a meeting on the progress of the preparatory work on the Sea Games on 20 March, under the chairmanship of Standing Deputy Prime Minister Somsavat Lengsavad.

The sub-committees for organizing the Sea Games reported at the meeting that the inauguration and closing ceremonies of this sporting would be different
from the past Sea Games.

The Standing Deputy Prime Minister stressed on the policy of usage of local products at this coming sporting event and on the need to get the Lao national athletes to practice at the training centre after the Lao New Year.

He also said the financial sub-committee has approved 90 billion kip to fund other preparatory works.

For the senior sports officials, they would be accommodated in eleven standard hotels and 200 rooms had been set aside specially for them, said Mr Somsavat.

To ensure spectacular shows during the opening and closing ceremonies of this sports event, there will be 8,000 performers, and they would be rehearsing their sequences soon, said the Standing Deputy Prime Minister.

Last but not least, he asked all sub-committees to be conscientious, to complete their work on schedule and to take care of the welfare of the athletes.


 